Project A has a cost of Rs.52.125 and expected cash flows are Rs.12,000 per year for next 8 years and its cost of capital is 12%.
a) What is the project"s net present value?
b) due to inflation factor if cost of capital raises to 15% than what would be the effect of this change on NPV of the project?